Force majeure, also known in Philippine law as a fortuitous event, refers to an extraordinary event that may excuse a party from liability for failing to perform an obligation.However, not every unexpected difficulty automatically qualifies as force majeure. Under Philippine law, the event must meet the legal requirements, and the party invoking it must not have contributed to the loss or non-performance.
Article 1174 of the Civil Code provides that, except when the law provides otherwise, when the parties stipulate otherwise, or when the nature of the obligation requires the assumption of risk, no person is liable for events that “could not be foreseen, or which, though foreseen, were inevitable.”
In simple terms, a party may be excused from liability when an extraordinary event makes performance impossible, provided that the event was truly beyond the party’s control and the legal requisites are present.
A party cannot simply claim force majeure because performance became difficult, inconvenient, delayed, or more expensive.
For a fortuitous event to excuse non-performance, the event must generally be independent of the party’s will, unforeseeable or unavoidable, and must make it impossible to perform the obligation in the normal manner.
The party invoking force majeure must also be free from participation in, or contribution to, the loss or injury. If the party’s own fault or negligence contributed to the non-performance, force majeure may not apply.
Parties may also include a force majeure clause in their contract. This clause may define what events will be considered force majeure between them, such as certain government acts, strikes, emergencies, or other extraordinary circumstances.
However, contractual stipulations must still comply with the law and must not violate morals, good customs, public order, or public policy.
Because of this, the actual wording of the contract matters. A force majeure clause should be reviewed carefully to determine whether the event is covered and what the parties are required to do when such an event occurs.
Events such as supply shortages, shortage of cement, typhoons, power failures, or water interruptions may be considered force majeure depending on the circumstances.
The key point is that the event must be proven, and there must be a clear connection between the event and the failure to perform the obligation.
For example, it is not enough to say that a typhoon occurred. The party invoking force majeure must show how the typhoon directly prevented performance and that the party did not contribute to the delay, damage, or loss.
Force majeure is highly dependent on facts.
A party claiming force majeure should be able to show what happened, when it happened, how it affected performance, and why performance became impossible despite reasonable efforts.
This is why notices, documentation, correspondence, government issuances, supply records, utility advisories, and other evidence may be important in determining whether force majeure applies.
Force majeure under Philippine law may excuse a party from liability for non-performance, but only when the legal requisites are met.
The event must be extraordinary, unforeseeable or unavoidable, and must directly prevent performance. The party invoking it must also show that it did not contribute to the loss or non-performance.
For businesses and contracting parties, the safest approach is to have a clear force majeure clause and to seek legal advice when an extraordinary event affects contractual obligations.
Attorney Ralph Borja Bodota
Attorney Roberto Narvasa Batungbacal
This article is for general informational purposes only and does not constitute legal advice. For more questions, feel free to send us an email.